IV .Technical Parameter
Model
|
Coil master
|
Coil width
|
700 ~ 1778mm
|
Coil OD
|
1100 ~ 2200mm
|
Coil ID
|
>457mmm
|
Coil
weight
|
1000-26000kg
|
Packing
material
|
PE/LLDPE
stretch film/PVC
ID:76mm
OD:100-250mm
Width:250mm
|
Shutter speed
|
app.2-3m/sec
|
Overlap rate
|
20%
~ 90%
|
Power
output
|
app 23KW
|
Power
voltage
|
480V, 3
phase, 60 Hz
|
Air
supply
|
6~8kgf /cm2
|
V. Machine Installation
1. This automatic coil packing machine system is
composed of blocker roller stations,
guide rail, main machine, trolley,
hydraulic system, shuttle, packing material release & storage station, U-type
orbital, automatic mechanical hand, signal detection
system, electric circuit system, electric cabinet and etc.
2. The machine shall be mounted in dry and
dust free environment.
3. The machine shall be mounted on flat and
hard ground, where the ground
load should be more
than 10t/ m2.
4.
Power supply should be in
accord with states in the nameplate of the
machine.
5.
Only trained personnel can be
allowed to enter the installation site.
6.
The entire installation shall
be done under the power supply is cut off.
7.
As the machine has been
transported and moved, all flexible components
shall be inspected carefully.
8.
Install the guide rail as the
design drawing on the ground horizontally,
then place trolley on guide rail to make
sure the trolley can moved smoothly.
9.
Put main engine/machine in the
trolley, machine should be perpendicular
to the trolley.
10. Install the U-type orbital and shuttle as the design drawing.
11. Install the hydraulic station and relevant pipelines.
12. Place three blocker roller stations,
electric wire trunking, signal
detection coil packaging machine system in correct positions according to the drawing.
13. Connect and check electric circuit system well as the electric
diagram.
14. Connect the power supply after installation complete.
15. Move the main coil packaging machine to three blocker roller stations in separate
in “Manual” mode and check their signals.
16. Calibrate the three blocker roller stations according to the stop
positions
of the
main engine/machine.
17. Operate each operation in “Manual” mode. After confirming there is
no
problem,
operating them again in “Auto” mode.